You are the project manager for a new project in the IT department at work and have figured out the following dependencies:

Draw a network diagram and answer the questions below:
You are the project manager for a new project in the IT department at work and have figured out the following dependencies:

(a)    Activity 1 can start immediately and has an estimated duration of 3 units.
(b)    Activity 2 can start after activity 1 is completed and has an estimated duration of 3 units.
(c)    Activity 3 can start after activity 1 is completed and has an estimated duration of 6 units.
(d)     Activity 4 can start after activity 2 is completed and has an estimated duration of 8 units.
(e)    Activity 5 can start after activity 4 is completed and after activity 3 is completed and this activity takes 4 units.

I.    Draw this activity follow and their dependencies.
II.    Answer the following questions:
a.    What is the duration of the critical path?

b.    What is the float of activity 3?

c.    What is the float of activity 2?

d.    What is the float of the path with the longest float?

e.    The resource working on activity 3 is replaced with another resource who is less experienced.  The activity will now take 10 units. How will this affect the

project?  Explain.

f.    After some additional arguing between stakeholders, a new activity 6 is added to the project.  It will take 11 units to complete and must be completed before

activity 5 and after activity 3.  Management is concerned that adding the activity will add 11 units to the project.  Another stakeholder argues the time will be less

than 11 units.  Who is correct?  Explain.  (Note:  begin with the project after Activity 3 has been increased to 10 units as directed in Problem 3, Question II(e)

READ ALSO :   the Financial Contributions from Trust in

above.)

Problem Four:
Considering the following data:

Activity    Preceding Activity    Estimated in Units
Start        0
D    Start    4
A    Start    6
F    D, A    7
E    D    8
G    F, E    5
B    F    5
H    G    7
C    H    8
End    C, B    0

Answer the following questions:

(a)    What is the duration of the critical path?

(b)     What is the float of activity B?

(c)    What is the float of activity E?

(d)     What is the float of activity D?