Academic Help Online

Imagine that you are the financial manager for a firm, and your company has a WACC of 4.5%. Two district managers would like funds to pursue a project, and are asking for your approval based on their projected financials.

Project A costs $180,000 today, and will give the company $25,000 profit per year for the next 15 years.

Project B costs $275,000 today, and will give the company $30,000 profit per year for the next 20 years.

If the discount rate is 4.5%, which project would you pursue? Why?

Use a financial model for this question, and explain/interpret your answer.

READ ALSO :   Academic Help Online