Please help with this question:

1. A construction project consists of the following activities as mentioned in the table:

Draw the AON network for the project,

a)What will be the minimum project completion time and how much it would cost?

b)If the overhead costs are 5/day, at what duration would total cost be a minimum?

c)Draw the direct indirect and minimum cost curve. Give your argument as a contractor as well as client to choose the appropriate minimum cost duration.

d)If there is a penalty of 10/day if the project exceeds 27 days and a bonus of 10/day if the project is completed before 27 days, will the minimum cost and optimum duration would be same or different and give your comments.

Activity

Predecessor

Normal Duration

Normal Cost

Crash Duration

Crash cost

A

1

10

1

10

B

A

2

20

2

20

C

A

4

30

1

40

D

B

5

50

3

60

E

C

6

60

4

65

F

C

7

70

5

76

G

E

8

80

6

90

H

D,F

9

90

7

98

I

G,H

10

100

8

110