1. GEOCON SEALANTS AND SHEA-JONES MANUFACTURE SPECIALIZED EQUIPMENT FOR SEALING TUNNELS. THE WASHINGTON METRO SYSTEM HAS A PROBLEM WITH GROUNDWATER CAUSING ELECTRI-CAL PROBLEMS IN THE VENTILLATION SYSTEM. THE TWO COM-PETING COMPANIES HAVE SUBMITTED THE FOLLOWING COST PROPOSALS TO THE TRANSIT AUTHORITIES.
ALTERNATE A ALTERNATE B
GEOCON SHEA-JONES

INITIAL $100,000 $150,000
COST

OPERATION & $2200/YR $1200/YR
MAINTENANCE

TECHNICAL $1500 $1200
SUPPORT/ YEARS 2 AND 4 YEARS 3 AND 6

EQUIPMENT $1000/YR $1500/YR
UPGRADE YEARS 2 AND 4 YEARS 3 AND 6

SALVAGE $40000 $60000

SAVINGS $35000/YR $35000/YR
ON TRANSIT
SHUTDOWNS

SAVINGS $10000/YR 11%/YEAR
INCREASE START YEAR 2 START YEAR 3

INTEREST
COST 6% CP QUARTERLY 2% CP MONTHLY
SAVINGS 1.5%/YR 1.5%/YR

USEFUL 4 YRS 6 YRS
LIFE

-2-

CE 3361 NAME:____________________
PROJECT IA
DUE: 8 OCTOBER 2015
SHOW ALL WORK AND CALCULATIONS
1. WHAT ARE THE EFFECTIVE ANNUAL INTEREST RATES ON COST?

(5) ALTERNATE A

(5) ALTERNATE B

2. WHAT IS THE PAYMENT PERIOD?

(5) ALTERNATE A

(5) ALTERNATE B
3 CONSTRUCT THE CASH FLOW DIAGRAM OF EITHER ALTERNATE A
(GEOCON) OR ALTERNATE B (SHEA) TO MAKE AN ECONOMIC
ANALYSIS COMPARISON OF THE TWO ALTERNATIVES